Exam: Cloud Digital Leader 0 Likes
Your organization needs a large amount of extra computing power within (Digital Leader)
Your organization needs a large amount of extra computing power within the next two weeks.
After those two weeks, the need for the additional resources will end.
Which is the most cost-effective approach?
A) Use a committed use discount to reserve a very powerful virtual machine.
B) Purchase one very powerful physical computer.
C) Start a very powerful virtual machine without using a committed use discount.
D) Purchase multiple physical computers and scale workload across them.
Solution
Correct answer: C) Start a very powerful virtual machine without using a committed use discount.
For a short-term, two-week burst of additional computing power, the most cost-effective approach is likely to use a cloud computing solution.
Explanation:
A. Using a committed use discount to reserve a very powerful virtual machine is more suitable for long-term commitments, not a short-term burst of two weeks.
B. Purchasing one very powerful physical computer involves upfront costs and may not be as flexible or cost-effective as a cloud solution, especially for a short-term need.
C. Starting a powerful virtual machine without using a committed use discount allows you to quickly provision resources and pay for only the compute power you use during the two weeks.
D. Purchasing multiple physical computers and scaling the workload across them involves higher upfront costs, potential over-provisioning, and is less flexible for a short-term burst.
In conclusion, option C is likely the most cost-effective approach for a short-term need of extra computing power within the next two weeks.